SSE invests a record £2.6bn in six months, with about 70% going into electricity networks
The energy group expects to spend more than £5bn this year and says gas storage at Atwick in East Yorkshire will start to be wound down from summer 2027 without government support.
By Daily Oracles News Team2 min read
SSE spent a record £2.6bn on investment and capital projects in the six months to 30 September, 63% more than a year earlier, and around 70% of it went into its regulated electricity networks. The company, which is a year into a five-year £33bn investment plan, said on Wednesday that it still expects to spend more than £5bn over the full year to March 2027.
Adjusted operating profit rose 68% to £1,103.4m from £655.0m, and adjusted earnings per share rose to 66.5p from 36.3p. Regulated networks produced around two thirds of adjusted operating profit. The interim dividend is 22.9p a share, up from 21.4p and set at a third of last year's full-year payout.
SSE kept its forecast of adjusted earnings of 168p to 193p a share for 2026/27 and its target of 225p to 250p for 2029/30.
Networks
Investment in SSEN Transmission, which runs the high-voltage grid in the north of Scotland, nearly doubled, and its adjusted operating profit doubled. Construction has started in full or in part on all 11 of its major transmission projects, which include the Spittal to Peterhead HVDC link, the Lewis Hub and the Banniskirk substation. The Scottish Government granted marine consent for the EGL3 project last week, and seven further consent decisions are expected during 2026 and 2027.
The value of SSE's regulated electricity network assets, measured as the regulatory asset value, rose to £17,874m at the end of September from £14,225m a year before.
SSEN Distribution, which serves around 4m homes and businesses in central southern England and the north of Scotland, will submit its business plan for the next price control period, RIIO-ED3, in the coming days. SSE said the plan proposes baseline and uncertainty-mechanism spending 50% higher than in the current period, to cope with rising electricity demand and keep the network resilient.
Wind, hydro and gas
About 150 turbines are now installed across the Dogger Bank wind farm, including 52 at Dogger Bank B, and cable laying for Dogger Bank C is nearly finished. SSE still aims to take a final investment decision on the 1.4GW Berwick Bank B wind farm in the second half of 2027 and has locked in around 60% of the expected debt at swap rates below 5%. It expects consent for the 0.8GW Arklow Bank project in Ireland in December, while the 1.4GW Coire Glas pumped hydro storage project is waiting for an Ofgem decision on a cap-and-floor funding mechanism.
In gas storage, SSE said existing market arrangements do not support continued operation of fast-cycle sites, and that price spreads were not emerging to keep Atwick, near Hornsea, running commercially. Unless the government intervenes, it expects to start rewatering the caverns at Atwick, the first step towards decommissioning, in summer 2027.
Dates for shareholders
The shares go ex-dividend on Thursday 10 December and the dividend will be paid on Friday 5 February 2027. SSE plans a third-quarter trading statement in early February and full-year results on 26 May 2027.